I flew over Skandi Artic berthed at Invergordon yesterday 11th ,lots of space cleared on the deck, supports being placed for something to be lowered into place. This press release explains what is in progress..
Technip Norway has been awarded by ConocoPhillips Skandinavia AS a lump sum contract for the Ekofisk VA subsea water injection project located in block 2/4 on the Norwegian Continental Shelf.
This contract provides for the installation, tie-in and commissioning of subsea facilities between the existing Ekofisk facilities and a new eight well subsea injection template (2/4VA).
The detailed design and the other equipment will be provided by ConocoPhillips. Offshore installation is scheduled for 2009.
Installation will be performed by several vessels including Technip’s new-built diving support vessel, the Skandi Arctic.